On the frontend of UpStream projects, you will see that a “Progress” percentage is visible. This Progress shows how far you have progressed with your project. That percentage is shown in the screenshot below.

![image](https://support.kelsiem.com/rails/active_storage/blobs/redirect/eyJfcmFpbHMiOnsibWVzc2FnZSI6IkJBaHBBa0FQIiwiZXhwIjpudWxsLCJwdXIiOiJibG9iX2lkIn19--62f543a0f48770630c00c5113d4b624847eb07b3/project-progress-1024x239.png)

In the image above, the overall project progress is 51%.

The overall progress of a project is calculated from the Tasks on a project.

In the image below, you can see four Tasks. The Tasks have a total percentage of 205%.

![image](https://support.kelsiem.com/rails/active_storage/blobs/redirect/eyJfcmFpbHMiOnsibWVzc2FnZSI6IkJBaHBBa0lQIiwiZXhwIjpudWxsLCJwdXIiOiJibG9iX2lkIn19--0dbcf93ce5109b2965528ac89400078256d23f3a/tasks-progress-1024x411.png)

So let’s do the final calculation for project progress … If you divide 205% by 4 you arrive at 51.25 which is then rounded down to 51%.